On this February 6, the ammunition elevator of the NMM moved to the ammunition bunker.
Brothers v.d. Putten was there again to do this job for us.
Construction of rails, Bemo-rail is laying of rails
In the past period, Bemo-rail has laid approx. 100 m of rails and concrete
This makes it possible to walk through this part as at the time of the war.
Continue reading “Construction of rails, Bemo-rail is laying of rails”
Placement of fire doors
Last month Metaglas installed 2 fire doors in the ammunition bunker. This is one of the necessary measures to be able to exhibit museum pieces in the ammunition bunker and thereby guarantee the fire safety of visitors and volunteers.
Continue reading “Placement of fire doors”
Glass walls in the audit office
Despite these times of corona in which we cannot receive visitors, work on the museum continues.
This week, glass partition walls were installed by the company Metaglas. With this, the calculators are safely behind glass.
Frames FL246
FL246 ammunition bunker blasted and whitened
Reinforce masonry wall
Lifts lintel
apply insulation observation post
After the installation of the plastic plates on the underside of the roof, it was now the turn of the inside of the roof.
Pluimers Isolatie has provided the inside of the roof with insulation.
With this we hope to prevent condensation from moisture.
Work Precium
A film about the work of Precium.